WESTERN Power Company Limited (WPCL) is targeting more than US$600 million in debt financing for its US$800 million Ngonye Falls hydro-electric power project in Sioma, Western Province, with two regional financiers mandated to lead the fundraising ahead of construction scheduled to start next year.
This follows the signing of a debt arranging mandate with Development Bank of Southern Africa (DBSA) and Stanbic Bank at the Zimbabwe-Zambia Energy Projects Summit (ZIM-ZAM 2026) on Tuesday.
The two banks will mobilise the needed financing to facilitate the development of the 180-megawatt power generation project in Western Province.
WPCL head of corporate finance Dean Horton said in an interview that the remaining funding will come from equity contributions by the project sponsors – Lunzua Power Company, Infracom Africa and Africa Power Partners (APP).
Mr Horton said the company expects to conclude the debt-raising process by early next year to mid next year to pave way for construction to start.
“This is an US$800 million project, so we are hoping to raise US$600 million in debt and the balance will be funded by the sponsors,” he said.
Mr Horton said construction will take about 42 months, with Power China International Group serving as the engineering, procurement and construction (EPC) contractor.
The project is expected to create more than 2,000 jobs during the construction stage and over 100 permanent employment opportunities once operational.
Mr Horton said the development will strengthen national energy security by adding 180 megawatts of dispatchable baseload renewable electricity to the national grid.
Zambia’s installed electricity generation capacity stands at 4,722.3MW, with solar accounting for approximately 21.76 percent of it.
The power to be generated by WPCL will be supplied to Zesco Limited under a 25-year power purchase agreement (PPA).
Mr Horton said the project supports Government's priority of expanding reliable electricity generation to drive economic growth in mining and manufacturing.
Unlike solar and wind energy, which depend on weather conditions, he said the run-of-river hydro-power project is designed to provide a more consistent electricity supply.
“This is high-quality power. It is not intermittent power like wind or solar. This is run-of-river and it operates all the time,” he said.
Mr Horton said the project is also designed to withstand climate variability with more than 100 years of historical Zambezi River flow data from the Zambezi River Authority (ZRA) informing projections of its power output.
He said the historical data will enable the company to assess seasonal river patterns and predict generation capacity more reliably.
Mr Horton said the project will contribute to Zambia's sustainable energy generation while providing dependable electricity to support growing demand.